Sunday, September 8, 2013

Basin pulls substation from battlefield

Basin pulls substation from battlefield



KILLDEER, N.D. — Basin Electric Power Cooperative said Wednesday it won't build a substation in the historic Killdeer Mountain battlefield area, but it's still planning to build a major transmission line through the heart of where the battle was fought.
The co-op's plans were detailed in a hearing that started in the morning and ended in the evening at Killdeer, just miles from the controversial location.
The Public Service Commission held the hearing to learn why it should waive certain requirements and move directly to issuing a route permit for a 200-mile transmission line that will start at the Antelope Valley Station near Beulah and end near Tioga.
The co-op wants to send another 500 megawatts of electricity into the oil patch to meet an ever-growing appetite for power in the booming oil development area, particularly in the McKenzie County region.
Commission President Brian Kalk said it could be two months before the commission makes any decision and even that will likely be pending federal approval under the National Environmental Policy Act.
The federal OK is needed because Basin plans to use USDA financing for the $375 million project.
Basin doesn't expect any federal decision until March 2014.
Much of Wednesday's hearing was spent sorting out the confusion caused by the recent announcement that the National Park Service, though its American Battlefield Protection Program, has approved a $90,000 grant to study and survey the battlefield for possible inclusion into a National Registry of Historic Places. The study contract was awarded to North Dakota State University's Center for Heritage Renewal.
Basin's engineering manager Duey Marthaller said the co-op didn't learn of the study until early last week and moved immediately to remove a 12-acre substation, but still wants to proceed with the line.
The battlefield study area is about 26 square miles on the south-facing slope and plains of the mountain area. Approximately 48 single pole structures 115 feet high would be spaced across it.
Aaron Barth, who will assist in the battlefield study, said the center didn't know that the battlefield study and the proposed power line were in conflict until the Tribune's story on the issue last week.
"We applaud the development, but we'd like to find some other way around here," Barth said.
Commissioner Julie Fedorchak said she wasn't happy with the apparent lack of communication.
"This is a very disturbing unfolding of events in the last week and a half. I would hope you all in cultural resources would get together to avoid this in the future. This not showing up on the State Historical Society's radar until a week before (the hearing) — something is off there," Fedorchak said.
Commissioner Randy Christmann wasn't pleased either, but for a different reason.
Christmann chastised Barth, saying none of the landowners were aware their private land was now inside a study area until the Tribune story.
"I'd be offended if a government agency took something this far without talking to me first," Christmann said.
Killdeer Mountain landowner Craig Dvirnak said he owns more than six sections inside the battlefield study area. He said he's neutral on the transmission line, but he is against the proposed study.
"All they've done is instilled mistrust. They should have gotten the landowners on board from day one. With federal money and the Native American culture, when you mix the two, it's never a good outcome for the landowner," Dvirnak said.
The 1864 Battle of the Killdeer Mountain has been called the largest military and Plains Indian engagement of the Great Plains. Barth said it's arguably the most important historic site in North Dakota.
Gerard Baker, an enrolled member of the Three Affiliated Tribes who has a 35-year career with the National Park Service, said more tribal views are needed, especially from the Sioux tribes that were engaged in the battle.
He said the battlefield should be avoided.
"I encourage you to move it (transmission line) out of the area so that there can be a pure area where people can stand in the middle of the battlefield and talk about what they were fighting for for their children and their grandchildren," Baker said.
Basin's environmental manager, Chris Miller, said the transmission line project has been in the works for three years and the corridor was developed with comment from the public.
He said the co-op will agree to recommendations from the State Historical Society that were issued Tuesday. It will move the substation, assess the visual effects of the transmission line from both the Medicine Hole on top of the mountain and from the battlefield historic monument, use a magnetometer along the line route inside the battlefield area to find artifacts, and conduct more archaeological testing if necessary.
Miller said its options are limited because of the nearby highway and an existing transmission line.
Beside the proposed line and based on booming load growth, Basin said it is also looking at building another transmission line around the east side of the Killdeer Mountains. It may use a route studied as an alternative to the one on the table Wednesday.
Theodore Roosevelt National Park Superintendent Valerie Naylor said presenting two alternative routes in an environmental document and then building in both of them is not in the spirit of planning and disclosure.
"The alternatives should be out there so that the power line could be built without impacting these cultural areas. If both are built, it's hardly an alternative," she said.

Thursday, September 5, 2013

Basin scraps substation in Killdeer Mountains area

Basin scraps substation in Killdeer Mountains area

Updated 5:27 am, Thursday, September 5, 2013

KILLDEER, N.D. (AP) — 
Basin Electric Power Cooperative is scrapping plans to build an electrical substation in the Killdeer Mountains area of western North Dakota, but is still planning to build a transmission line in the area of a historical 1864 battle between Army soldiers and American Indians.
The utility wants to build the 200-mile line from theAntelope Valley Station power plant near Beulah to a spot near Tioga to deliver more electricity to the Bakken oil fields, where there is a growing demand for power. State regulators held a hearing in Killdeer on Wednesday about the proposal. Public Service Commission President Brian Kalk said it could be two months before the group makes a decision on approval.
The proposed $300 million project — which also needs federal approval because Basin plans to seek financing from the U.S. Department of Agriculture — comes at a time when an alliance is trying to protect the Killdeer Mountains region from oil drilling.
The transmission line route and the substation were proposed in an area where soldiers led by Army Brig. Gen. Alfred Sully clashed with Sioux warriors more than 200 years ago. The battlefield is now a state historic site, and the National Park Service has approved a $90,000 study to be led by North Dakota State University on whether it should be considered for federal protection.
Basin's engineering manager, Duey Marthaller, said the co-op didn't learn of the study until early last week and moved immediately to remove a proposed 12-acre substation from the area. Substations help distribute electricity to consumers.
Basin's environmental manager, Chris Miller, said the transmission line project has been in the works for three years and that the corridor was developed with comment from the public. Options are limited because of a nearby highway and an existing transmission line, he said.
The co-op will agree to recommendations from the State Historical Society, including moving the substation and assessing the visual effects of the transmission line, Miller said.
Valerie Naylor, superintendent of Theodore Roosevelt National Park in western North Dakota, said portions of Basin's power line would be seen from up to 30 percent of the park's North Unit.
Gerard Baker, an enrolled member of the Three Affiliated Tribes and a 35-year career veteran of the National Park Service, said more tribal input is needed, especially from the Sioux tribes that were engaged in the 1864 battle.
"I encourage you to move it (transmission line) out of the area so that there can be a pure area where people can stand in the middle of the battlefield and talk about what they were fighting for, for their children and their grandchildren," he said.

Wednesday, September 4, 2013

Basin Electric plans power line through Killdeer Mountains

Published September 04, 2013, 12:00 AM

Basin Electric plans power line through Killdeer Mountains

KILLDEER — Basin Electric Power Cooperative will have to answer to a lot of angry people at a public hearing in Killdeer today. The company, citing booming oil development and its ripple effects, has proposed a new transmission line that would go through the Killdeer Mountain Battlefield site, alarming many.
By: Katherine Lymn, The Dickinson Press

KILLDEER — Basin Electric Power Cooperative will have to answer to a lot of angry people at a public hearing in Killdeer today.
The company, citing booming oil development and its ripple effects, has proposed a new transmission line that would go through the Killdeer Mountain Battlefield site, alarming many.
The $300 million project would route a 200-mile, 345-kilovolt transmission line from the existing Antelope Valley Station near Beulah, west through Killdeer and then north through Williston, ending at a substation near Tioga.
It would run through the boundaries of a National Park Service study led by North Dakota State University history professor Tom Isern, who characterizes the battlefield as the most significant historic site in the state.
The 1864 Battle of Killdeer Mountain was a faceoff between native Dakota and Lakota fighters and Brig. Gen. Alfred Sully’s forces. With more than 2,000 fighters on each side, Isern said, “it’s the largest military engagement ever to take place on the Great Plains.”
For its entire nine-state service area, Basin projects needing to grow by more than 1,600 megawatts by 2025 — and 1,000 megawatts of that is just for oil-related growth.
“There’s a lot of demand being placed on everybody because of what’s going on in western and northwestern North Dakota,” Basin spokesman Daryl Hill said. “This is just one part of the challenges everybody faces to cope or to keep up with this oil development that’s occurring.”
Hill said an archeologist Basin hired didn’t see anything of significance in a preliminary survey, but Basin only recently learned of the NDSU study, so “this isn’t the end of the story.”
Basin spokeswoman Mary Miller cautioned, though, that Basin has had this route planned for a while and it’s not the company’s intent to move the line.
Some opponents of the project have questioned whether Basin’s archeologist did a thorough enough look at the project site.
Conservationist Rob Sand, who lives near the site and fights for the mountain’s preservation with the Killdeer Mountain Alliance, said the battlefield is not just a 1-acre site with a monument on it, but in fact “covers a great deal of area.”
“Unfortunately it had to be a citizens’ group that noticed it and put it together,” he said.
“I think [Basin] looked at each spot where they were gonna put a power pole and just did a minimal survey — a required survey — of that and didn’t look at the big picture,” Sand said.
Public Service Commission Chair Brian Kalk said the size of this project is the reason for three different public hearings — Tioga and Williston will also have hearings on Thursday and Thursday, Sept. 12, respectively.
“Of all the things that we do, power lines are by far the most difficult and the most contentious,” he said.
The PSC can’t tell a company how to do a project, but it can reject an application and explain why, Kalk said.
Sand said he’s also concerned with what the power lines would do to the viewscape.
“This is a real serious problem and needs to be resolved,” Sand said, “and I’m sure hoping that Basin Electric and the Public Service Commission will see this as an opportunity to do the right thing and move it off of the battlefield for sure but also look at the whole viewscape of the Killdeer Mountains.”
Kalk encouraged members of the public to bring their own recommendations for the project if they’re unhappy with the current plan.
This project is the latest in a series of apparent threats to the Killdeer Mountains, as oil development seeped in and the Alliance has been working to stop further drilling.
“It’s pretty overwhelming to try to even think what’s gonna happen because [the Mountains] could easily just be covered with oil wells and with roads and with power lines,” Sand said.
“We have to be hopeful that there can be some kind of a sensitive resolution to these problems.”
The public hearing will be at Killdeer City Hall, 165 Railroad St. SE at 9:30 MDT.