The Battle to Save Killdeer Mountain
Tuesday, September 16, 2014

Records of Decision

›
So far I can find nothing regarding the Records of Decision in the Federal Register. Record of Decision for the USDA USFS can be found on th...

›
It seems appropriate to mark the day of the transmission line approval with two quotes from two significant figures in US history who had bo...
Monday, September 15, 2014

Record of Decision for Basin Transmission Line Follows Hoeven Effort to Bring Parties Together in March New Line Will Bring More Power to Western North Dakota Communities

›
Sep   15   2014 Record of Decision for Basin Transmission Line Follows Hoeven Effort to Bring Parties Together in March New Line Will ...

Basin Electric gets approval for delayed transmission line

›
Basin Electric gets approval for delayed transmission line 8 hours ago    •    By  Jessica Holdman Basin Electric Power Coo...
Tuesday, July 15, 2014

For Immediate Release: July 26 All-Day Family-Friendly Event in Dunn Center Commemorates Killdeer Mountain History and Conflict of 1864 (Dunn Center, ND)

›
Dunn County Historical Society & Museum / 153 Museum Trail, Dunn Center, ND / PO Box 145, Killdeer, ND 58640 dunncountymuseum@ndsupernet...
Wednesday, June 18, 2014

Section 106 Consultation Meeting Transcript

›
UNITED STATES DEPARTMENT OF AGRICULTURE RURAL UTILITIES SERVICE AVS-NESET 345 kV TRANSMISSION LINE PROJECT Section 106 TRANSCRIPT OF CON...

EIS-0478: FINAL ENVIRONMENTAL IMPACT STATEMENT

›
Antelope Valley Station to Neset Transmission Project, Mercer, Dunn, Billngs, Williams, McKenzie, and Mountrail Counties, North Dakota ...
›
Home
View web version
Powered by Blogger.